On the T-14-24 Skole–Slavske highway in the village of Hrebeniv, we are building a bridge across the Opir River.
The T-14-24 highway provides a stable transport link between communities and is important for the development of tourism, the economy and social infrastructure in the mountainous region of Lviv Oblast.
Work on the installation of bored piles, caps, columns, girders and trusses has already been completed. The installation of beams has begun. The next step will be to install the deck slab, formwork, transition slabs, sidewalks on both sides and curbs.

The length of the newly built structure will be 64 meters. We will also build approaches to the bridge, which will connect it to the road.
For reference. The bridge was built in 1961. It has undergone only one major repair. Therefore, the bridge was in disrepair. After inspection, experts decided to build a new structure near the old one. This will allow construction work to be carried out without blocking traffic.